Project Report: From Jetty to the erection of a 454 tonnes Flash Column at the Ammonia & Urea 3500 MTPD Plant in Bontang, East Kalimantan

Discharging from MV Palmarola by 2 x 450Tonne vessel gear

Discharging from MV Palmarola by 2 x 450Tonne vessel gear

Discharging from MV Palmarola by 2 x 450Tonne vessel gear

Discharging from MV Palmarola by 2 x 450Tonne vessel gear

122D1:163D Flash Column02

Mammoet SPMT 2x24axlelines ready to receive , after shifting others vessel 114-C

Received by Mammoet SPMT 2x24 axlelines in radius 12m from vessel side

Received by Mammoet SPMT 2×24 axlelines in radius 12m from vessel side

Received by Mammoet SPMT 2x24 axlelines in radius 12m from vessel side

Received by Mammoet SPMT 2×24 axlelines in radius 12m from vessel side

Transporting from Jetty to temporary Laydown area; distance 1km

Transporting from Jetty to temporary Laydown area; distance 1km

Laydown area on the road.

Moving to Erection point after around 7 days laid on elephant stool platform at road laydown
area

 

Manoeuvering at entrance gate to erection position .

Manoeuvering at entrance gate to erection position .

Manoeuvering at entrance gate to erection position

Manoeuvering at entrance gate to erection position

122D1/163D Flash Column arrive at erection point and pick-up by main crane CC-8800-1(1600T) and tailing crane CC-2800-1(600T).

122D1/163D Flash Column arrive at erection point and pick-up by main crane CC-8800-1(1600T)
and tailing crane CC-2800-1(600T).

Starting erection

Starting erection

Column in Vertical position

Column in Vertical position

Demag CC800 moved on SPMT's to new location

Demag CC8800 moved on SPMT’s to new location

 

IMG-20130720-00944

IMG-20130720-00946

IMG-20130815-01052

Erection bagging hopper 85ton L15mxW6.0xH6.0 by LR-1350 main and Tadano-Faun 160T capacity