Heavy Lift Specialist

Transport of 230 Tons Generator by means of RoRo ponton 1987

 

The transport of a 230 tons Generator from Smit Slikkerveer to the Power Plant Lage Weide near the city of Utrecht.

In order to get the generator on deck of the RoRo barge, but especially make it possible to roll-off at the unloading site as well, careful planning and calculations were needed to establish the correct deck height for the RoRo ramp beam.coupling