Heavy Lift Specialist
Nov 292013
 

Jumbo has recently completed her activities in the first stage of the Wiggins Island Coal Export Terminal Project in Queensland, Australia.

18 Nov 2013

Faripartner_lift_dusk-01The export terminal, when completed, will represent one of the largest such facilities in the world.

The project was planned meticulously, to ensure efficient operations. At one stage 2 J-class vessels were sailing from China, one day apart, one with gantry equipment which was discharged to barges for further transport to site and one with wharf decks which where directly discharged at the currently developed quay where in the future the coal ships will berth and be loaded from. This berth is located well outside the island to have unrestricted access to deep water. Safety, as with everything carried out by Jumbo, was given the highest priority.

Jumbo Jubilee lifts and discharges wharf deck

Work on the project commenced in May of this year, with the 1st of six consecutive voyages using mv Fairpartner.

Jubilee and FairpartnerThe project saw Jumbo transporting a range of large and heavy equipment from China to Australia. Amongst these were a number of gantries. The gantries were stacked and transported, with as many as seven being carried in one go, utilising most of the plentiful space available on the J-class vessels.

Jubilee offloadsThe largest piece of equipment was a 537t stacker bridge which was 126m in length. The stacker bridge needed to be lifted on to the vessel from port side, which was made possible by the J-class’ versatility and crane outreach. For the safe handling of this stacker a project specific lifting frame was developed which also acted as support for the stacker bridge during the ocean voyage.

Jubilee-offloads-16Jumbo’s inhouse engineering team was responsible for the design of a set of lifting beams that were versatile enough to deal with 8 modules of differing sizes and weights. The modules were transported two and three at a time to on-site location.

P1040035Jumbo’s involvement with the project is set to continue next year with the transportation of the final set  of wharfdecks and ultimately the transportation from Port Klang Malaysia of the shiploader weighing around 1,200t (LxWxH, 76.5x48x28.5) per may 2014 dates.

P1040040Therewith Jumbo performed a key roll in the successful development of the Wiggins Island Coal Expansion Terminal Project.